Eurotech Factory

Construction of new two storey factory unit – 3450m2 GIFA, associated external works, drainage and services.
+BREEAM very good rating
+ Rainwater harvesting and specialist filtering for factory processes
+ Stormwater attenuation tank
+ Landfill site
+ Ground stabilisation
The building was constructed at the perimeter of a landfill site. Foundations and substructure design incorporated ground stabilisation and methane ventilation and barriers. A specialised rainwater harvesting and regeneration system was designed to provide the facility to collect filtered rainwater and recycled rinse water for the factory to use in their manufacturing processes.

Value of project

£1,200,000

Single Stage Design & Build using JCT Design & Build 2005 Edition